1. TeraGrid Final Report:

  • Draft outline on the sharepoint server at: [TeraGrid Final Report SharePoint page]
    • Please review the draft and send and change suggestions toe John Gerber by Friday, July 8th. If you want to send a marked up copy to him, please turn on “track changes” before making your changes.


  • Here is the proposed schedule for creation of the TeraGrid Final Report. This schedule overlaps with the schedule for the next Quarterly Report, during July and August.
    1. Identify resources: AD, PI/User, RP, SAB – 6/14 to 6/24
      1. All current and past Ads
      2. All current and past RPs
      3. Selected key PI/Users with long TG association
      4. Selected SAB members
    2. Develop report format – 6/14 to 7/8
      1. Draft based on Guidance
      2. Review and revise draft
      3. Provide format document to those creating each section
    3. Collect “lessons learned” – 6/27 to 7/29
      1. Collect from identified resources
      2. Assign a group of resources to each AD?
      3. Come to agreement on which “lessons learned” will go in each section
    4. Develop report sections – 8/1 to 8/26
      1. Base on “lessons learned” for the section
      2. Base focus and length on guidance
        1. Impact to Science and Engineering (4-6 pages) – Dan Katz
        2. Impact to Researchers, Educators and the broader Community (4-6 pages) – Amit Majumdar, Sergiu Sanielevici
        3. Impacts to Education, Outreach and Training (4-6 pages) – Scott Lathrop
        4. Administration and Organization (6-8 pages) – John Towns
    5. Review and finalize report sections – 8/21 to 9/9
      1. Executive Summary (2 pages) – John Towns
      2. Introduction and Overview (3-4 pages) – John Towns
      3. Review by all Ads (RPs, others?)
    6. Assemble draft Final Report 9/12 to 9/16
      1. Review and finalize Final Report 9/19 to 9/23
      2. Ads (others?)
    7. Final edit of Report 9/26 to 9/30
      1. John Towns?



2. Other items

  •  ???