Extension-Integrated Project Plan

From TeraGrid Wiki

Jump to: navigation, search

IPP Document

Key Dates

Start-End Date Owner Task Status
6/1/09 - 6/12/09 Mike, Tim, John G Update TG Extension IPP Section draft 100%
6/15/09 - 6/19/09 ADs Distribute TG Extension IPP Section draft 100%
6/22/09 - 7/24/09 Mike, Tim, John G Update TG Extension IPP Section final version 100%
7/27/09 - 7/31/09 ADs Distribute TG Extension IPP Section final version 100%
8/3/09 - 8/28/09 Nancy Develop SGW Plan 100%
8/3/09 - 8/28/09 Scott Develop EOT Plan 100%
8/3/09 - 9/1/09 RPs Request to all sub-awardees to have all PY4 (Through July 31st 2009) to the GIG 100%
8/3/09 - 8/21/09 John G Develop first draft of TG Extension IPP 100%
8/3/09 - 8/21/09 TG EXT and Tim TG Extension Operations Definitions Spreadsheets filled out 100%
8/24/09 - 8/28/09 TG EXT and Tim Review TG Extension Operations common IPP text 100%
8/24/09 - 9/4/09 ADs Develop second draft of TG Extension IPP 100%
8/31/09 - 9/4/09 John G Build budget spreadsheet with areas/activities/FTE/$ 100%
9/7/09 - 9/11/09 All Review TG Extension IPP for completeness and acceptance 100%
9/7/09 - 9/11/09 All Budget review to confirm syncs with Extension Budget 100%
9/21/09 - 9/22/09 Mike, Tim, John G Post IPP to WIKI ( no institution specific SOWs posted) 100%
9/30/09 - 10/13/09 John G, Mike Create the WBS outline and send to ADs 100%
10/14/09 - 10/20/09 ADs ADs update WBS outline with quarterly milestones 100%